Réponse rapide : Chinese factories close for six public holidays a year, and two of them can make or break your supply chain: Chinese New Year (February 6, 2027 — a 6–8 week real-world disruption) and Golden Week (October 1–7 every year). The rule that saves you: work backwards. For sea freight arriving before CNY 2027, place orders by November–December 2026; air freight buys you until late December; express until mid-January at premium rates. Miss the window and your goods sit until March.

The Full Factory Holiday Calendar

Holiday2026 Dates2027 DatesReal Disruption
Chinese New YearFeb 15–23Feb 5–12 (CNY day: Feb 6)6–8 weeks total (slowdown → shutdown → ramp-up)
Qingming FestivalApr 4–6Apr 4–63 à 5 jours
Labour DayMay 1–5May 1–55 à 7 jours
Dragon Boat FestivalJun 22–24Jun 10–123–4 days
Mid-Autumn FestivalSep 29–Oct 1Sep 19–213–4 days
Golden Week (National Day)Oct 1–7Oct 1–71–2 weeks

Dates follow China’s State Council schedule, announced late each year — treat them as planning anchors and confirm with your supplier (or with us) each season.

Why CNY Is Not a One-Week Holiday

The official holiday is 7–8 days. The operational reality is 6–8 weeks:

  1. Pre-holiday slowdown (from mid-January): factories stop taking new orders, freight rates spike (GRI surcharges), and shipping space tightens
  2. Shutdown (~Feb 5–12, 2027): zero production; ports and trucking run skeleton crews
  3. Ramp-up (mid-February–early March): 10–30% of migrant workers do not return — factories restart understaffed, lead times stretch, and early batches carry higher defect risk

One more twist: CNY 2027 falls 11 days earlier than CNY 2026, so last year’s planning dates will leave you late this year.

Your Order-By Deadlines for CNY 2027

Work backwards from February 6:

Shipping ModeProduction Done ByOrder Placed By (typical 30-day production)
Fret maritimeEarly January 2027November–early December 2026
Fret aérienMid-January 2027Late December 2026
ExpressLate January 2027Mid-January 2027 (rates at peak)
After that—Your delivery window moves to March 2027

And do not forget Golden Week on the way: October 1–7, 2026 removes a full production week right in the middle of your Q4/CNY runway.

Month-by-Month Action Plan

How we help: our Yiwu warehouse receives and stores goods for 30 days free, so you can front-load production in December, consolidate in January, and ship the moment capacity allows — instead of paying rush rates for last-minute factory-direct dispatch.

Suggestions de liens internes :

Appel à l’action : Planning a Q1 2027 restock? [Register for free] and send us your SKU list now — we will confirm supplier shutdown dates and lock your production slot before the November rush.

Laisser un commentaire

Votre adresse e-mail ne sera pas publiée. Les champs obligatoires sont indiqués avec *