Мета-описание: China factory holidays 2026–2027: CNY 2027 (Feb 6) shuts production for 6–8 weeks. Full calendar plus order-by deadlines for sea, air and express.

dateModified: 2026-09-27

Краткий ответ: Chinese factories close for six public holidays a year, and two of them can make or break your supply chain: Chinese New Year (February 6, 2027 — a 6–8 week real-world disruption) and Golden Week (October 1–7 every year). The rule that saves you: work backwards. For sea freight arriving before CNY 2027, place orders by November–December 2026; air freight buys you until late December; express until mid-January at premium rates. Miss the window and your goods sit until March.

The Full Factory Holiday Calendar

Holiday 2026 Dates 2027 Dates Real Disruption
Chinese New Year Feb 15–23 Feb 5–12 (CNY day: Feb 6) 6–8 weeks total (slowdown → shutdown → ramp-up)
Qingming Festival Apr 4–6 Apr 4–6 3–5 дней
Labour Day May 1–5 May 1–5 5–7 дней
Dragon Boat Festival Jun 22–24 Jun 10–12 3–4 days
Mid-Autumn Festival Sep 29–Oct 1 Sep 19–21 3–4 days
Golden Week (National Day) Oct 1–7 Oct 1–7 1–2 weeks

Dates follow China’s State Council schedule, announced late each year — treat them as planning anchors and confirm with your supplier (or with us) each season.

Why CNY Is Not a One-Week Holiday

The official holiday is 7–8 days. The operational reality is 6–8 weeks:

  1. Pre-holiday slowdown (from mid-January): factories stop taking new orders, freight rates spike (GRI surcharges), and shipping space tightens
  2. Shutdown (~Feb 5–12, 2027): zero production; ports and trucking run skeleton crews
  3. Ramp-up (mid-February–early March): 10–30% of migrant workers do not return — factories restart understaffed, lead times stretch, and early batches carry higher defect risk

One more twist: CNY 2027 falls 11 days earlier than CNY 2026, so last year’s planning dates will leave you late this year.

Your Order-By Deadlines for CNY 2027

Work backwards from February 6:

Способ доставки Production Done By Order Placed By (typical 30-day production)
Морские перевозки Early January 2027 November–early December 2026
Авиаперевозки Mid-January 2027 Late December 2026
Экспресс Late January 2027 Mid-January 2027 (rates at peak)
After that — Your delivery window moves to March 2027

And do not forget Golden Week on the way: October 1–7, 2026 removes a full production week right in the middle of your Q4/CNY runway.

Month-by-Month Action Plan

How we help: our Yiwu warehouse receives and stores goods for 90 days free, so you can front-load production in December, consolidate in January, and ship the moment capacity allows — instead of paying rush rates for last-minute factory-direct dispatch.

Предложения по внутренним ссылкам:

Призыв к действию: Planning a Q1 2027 restock? [Register for free] and send us your SKU list now — we will confirm supplier shutdown dates and lock your production slot before the November rush.

Related reading: China sourcing calendar · Black Friday order deadlines · sourcing agent fee models

Related reading: platform comparison · Alibaba.com versus 1688 · buying from 1688 overseas

Want the exact number for your own shipment? Model it yourself in the order deadline shipping cost calculator.